Managing Product DeliveryThis is where the work is done in a Prince2 project, either by in-house teams or subcontractors. Once a Work Package is received, the deliverable defined in the work package is produced according to the agreed plan under the management of a Team Manager (in Prince2 terminology). This process deosn't define the methodology by which the products should be produced. It may be, for example, that a subcontractor doesn't use Prince2 at all. Prince2 therefore only defines the interfaces of Work Package input, the production of Checkpoint Reports, and the return of the completed product. |
|
|
Copyright©2006 Project Performance Consulting Ltd PRINCE2 is a Trade Mark of the Office of Government Commerce The PRINCE2 Cityscape logo is a Trade Mark of the Office of Government Commerce, and is Registered in the U.S. Patent and Trademark Office The MSP Spheres logo is a Trade Mark of the Office of Government Commerce M_o_R ® is a Registered Trade Mark and a Registered Community Trade Mark of the Office of Government Commerce |
|