Tolerance is one of the major controls of a Prince2 project, and is key to the concept of management by exception.

There is a recognition in Prince2 that no project ever goes exactly according to plan, and that managers need some leeway to make decisions and adjustments. When a plan is presented for approval, the approving body can set tolerances, or 'margins of error' within which managers can manouver without resorting to higher authority. If it is predicted that tolerances will be exceeded, then the manager is obliged to make an 'exception report' to escalate the problem to higher management where a decision can be made. In many cases, an exception plan will be required.

Tolerance can be set on any variable of the project, most usually on time and cost, but possibly on other factors such as expected benefits, quality or risk.

The use of tolerance across four layers of  management in a Prince2 project can be summarised like this:

Prince2 Tolerances

<<< Back

 

 

[PRINCE2 Tour |The Project Mandate][PRINCE2 Tour | Products of CS][PRINCE2 Tour | Products of DP][PRINCE2 Tour | Products of MP][PRINCE2 Tour | Products of SB][PRINCE2 Tour | Transition to CP][PRINCE2 Tour | Outputs from CP][PRINCE2 Tour | Products of SU][PRINCE2 Tour | Products of DP][PRINCE2 Tour | Products of Planning][PRINCE2 Tour | Products of Planning (2)][PRINCE2 Tour | Products of Planning (3)][PRINCE2 Tour | Products of IP][PRINCE2 Tour | Products of CS][PRINCE2 Tour | Products of CS (2)][PRINCE2 Tour | Business Case][PRINCE2 Tour | Organisation][PRINCE2 Tour | Project Assurance][PRINCE2 Tour | Project Support][PRINCE2 Tour | Product Based Planning][PRINCE2 Tour | Tolerance][PRINCE2 Tour | Stages][PRINCE2 Tour | Change Control][PRINCE2 Tour | Quality Review][PRINCE2 Tour | Project Management Team][PRINCE2 Tour | Plans][PRINCE2 Tour | Controls][PRINCE2 Tour | Management of Risk][PRINCE2 Tour | Quality in a Project Environment][PRINCE2 Tour | Configuration Management][PRINCE2 Tour | Change Control][PRINCE2 Tour | The Project Board][PRINCE2 Tour | Starting Up a Project][PRINCE2 Tour |Directing a Project][PRINCE2 Tour | Initiating a Project][PRINCE2 Tour | Controlling a Stage][PRINCE2 Tour | Managing Product Delivery][PRINCE2 Tour | Managing Stage Boundaries][PRINCE2 Tour | Planning][PRINCE2 Tour | Closing a Project]

 

Project Performance Online

 

Copyright©2006 Project Performance Consulting Ltd

PRINCE2 is a Trade Mark of the Office of Government Commerce

The PRINCE2 Cityscape logo is a Trade Mark of the Office of Government Commerce, and is Registered in the U.S. Patent and Trademark Office

The MSP Spheres logo is a Trade Mark of the Office of Government Commerce

M_o_R ® is a Registered Trade Mark and a Registered Community Trade Mark of the Office of Government Commerce

 

 

prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training