Products of the Controlling a Stage processVarious outputs from Controlling a Stage will need to make their way to the Project Board for review or decision making. These are: - Highlight Reports, summarising the current status of the stage - Escalated project issues or requests for advice from the Project Board for which the Project Manager needs 'ah-hoc' direction - Exception Reports, describing a situation which threatens the successful completion of the stage within tolerances previously set by the Project Board. |
|
|
Copyright©2006 Project Performance Consulting Ltd PRINCE2 is a Trade Mark of the Office of Government Commerce The PRINCE2 Cityscape logo is a Trade Mark of the Office of Government Commerce, and is Registered in the U.S. Patent and Trademark Office The MSP Spheres logo is a Trade Mark of the Office of Government Commerce M_o_R ® is a Registered Trade Mark and a Registered Community Trade Mark of the Office of Government Commerce |
|