PRINCE2 Tour | Products of Planning (3)

Products of the Planning Process

The role of the Managing Stage Boundaries process is to ensure that the transition from one stage of the project to the next is properly controlled. At this time, a  detailed plan must be produced for the next planned stage of the project which must be approved by the Project Board before that stage can begin.

Two types of plan can be produced at this point:

- a 'normal' plan for the next stage, produced when everything's going okay, and the previous stage has completed successfully

- an 'exception' plan for recovery from an exception situation during a stage, for example an overspend which exceeds pre-defined tolerance.

Detailed plans for a stage must also include the plans for Quality Control of the products to be produced in that stage.

<<< Back

 

 

[PRINCE2 Tour |The Project Mandate][PRINCE2 Tour | Products of CS][PRINCE2 Tour | Products of DP][PRINCE2 Tour | Products of MP][PRINCE2 Tour | Products of SB][PRINCE2 Tour | Transition to CP][PRINCE2 Tour | Outputs from CP][PRINCE2 Tour | Products of SU][PRINCE2 Tour | Products of DP][PRINCE2 Tour | Products of Planning][PRINCE2 Tour | Products of Planning (2)][PRINCE2 Tour | Products of Planning (3)][PRINCE2 Tour | Products of IP][PRINCE2 Tour | Products of CS][PRINCE2 Tour | Products of CS (2)][PRINCE2 Tour | Business Case][PRINCE2 Tour | Organisation][PRINCE2 Tour | Project Assurance][PRINCE2 Tour | Project Support][PRINCE2 Tour | Product Based Planning][PRINCE2 Tour | Tolerance][PRINCE2 Tour | Stages][PRINCE2 Tour | Change Control][PRINCE2 Tour | Quality Review][PRINCE2 Tour | Project Management Team][PRINCE2 Tour | Plans][PRINCE2 Tour | Controls][PRINCE2 Tour | Management of Risk][PRINCE2 Tour | Quality in a Project Environment][PRINCE2 Tour | Configuration Management][PRINCE2 Tour | Change Control][PRINCE2 Tour | The Project Board][PRINCE2 Tour | Starting Up a Project][PRINCE2 Tour |Directing a Project][PRINCE2 Tour | Initiating a Project][PRINCE2 Tour | Controlling a Stage][PRINCE2 Tour | Managing Product Delivery][PRINCE2 Tour | Managing Stage Boundaries][PRINCE2 Tour | Planning][PRINCE2 Tour | Closing a Project]

 

Project Performance Online

 

Copyright©2006 Project Performance Consulting Ltd

PRINCE2 is a Trade Mark of the Office of Government Commerce

The PRINCE2 Cityscape logo is a Trade Mark of the Office of Government Commerce, and is Registered in the U.S. Patent and Trademark Office

The MSP Spheres logo is a Trade Mark of the Office of Government Commerce

M_o_R ® is a Registered Trade Mark and a Registered Community Trade Mark of the Office of Government Commerce

 

 

prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training