Products of the Planning Process

During Initiating a Project, the project plan must be produced. This plan must provide sufficient information to the Project Board for them to decide whether to proceed with project, and must therefore include information on

- the products to be produced

- the major activities necessary

- an assessment of the risks associated with the plan

- effort and duration estimates

- key milestones

- the schedule and costs

- the key decision and review points.

The Planning process is used to produce this plan, which will probably be produced at two levels, described in the Plans component, and which will cover at least one Stage of the project.

<<< Back

 

 

[PRINCE2 Tour |The Project Mandate][PRINCE2 Tour | Products of CS][PRINCE2 Tour | Products of DP][PRINCE2 Tour | Products of MP][PRINCE2 Tour | Products of SB][PRINCE2 Tour | Transition to CP][PRINCE2 Tour | Outputs from CP][PRINCE2 Tour | Products of SU][PRINCE2 Tour | Products of DP][PRINCE2 Tour | Products of Planning][PRINCE2 Tour | Products of Planning (2)][PRINCE2 Tour | Products of Planning (3)][PRINCE2 Tour | Products of IP][PRINCE2 Tour | Products of CS][PRINCE2 Tour | Products of CS (2)][PRINCE2 Tour | Business Case][PRINCE2 Tour | Organisation][PRINCE2 Tour | Project Assurance][PRINCE2 Tour | Project Support][PRINCE2 Tour | Product Based Planning][PRINCE2 Tour | Tolerance][PRINCE2 Tour | Stages][PRINCE2 Tour | Change Control][PRINCE2 Tour | Quality Review][PRINCE2 Tour | Project Management Team][PRINCE2 Tour | Plans][PRINCE2 Tour | Controls][PRINCE2 Tour | Management of Risk][PRINCE2 Tour | Quality in a Project Environment][PRINCE2 Tour | Configuration Management][PRINCE2 Tour | Change Control][PRINCE2 Tour | The Project Board][PRINCE2 Tour | Starting Up a Project][PRINCE2 Tour |Directing a Project][PRINCE2 Tour | Initiating a Project][PRINCE2 Tour | Controlling a Stage][PRINCE2 Tour | Managing Product Delivery][PRINCE2 Tour | Managing Stage Boundaries][PRINCE2 Tour | Planning][PRINCE2 Tour | Closing a Project]

 

Project Performance Online

 

Copyright©2006 Project Performance Consulting Ltd

PRINCE2 is a Trade Mark of the Office of Government Commerce

The PRINCE2 Cityscape logo is a Trade Mark of the Office of Government Commerce, and is Registered in the U.S. Patent and Trademark Office

The MSP Spheres logo is a Trade Mark of the Office of Government Commerce

M_o_R ® is a Registered Trade Mark and a Registered Community Trade Mark of the Office of Government Commerce

 

 

prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training prince2 training